Construction Draw Schedule: How Draws Work and Avoid Delays

Category: Construction | By Cristina Johnson | 11 minute read | Updated Sep 6, 2022
Construction Draw Schedule: How Draws Work and Avoid Delays

A construction draw schedule is a milestone-based payment plan for a construction contract or loan. One published lender six-draw example allocates 20% to foundation, 20% to framing, 10% to windows and doors, 25% to rough-ins and drywall, 15% to trim, and 10% to final completion.

For a construction loan draw schedule, the document gives lenders, borrowers, builders, and inspectors the same payment roadmap. It shows when draw requests happen, what work needs verification, and which documents support each payment.

Key takeaways

  • One published lender's 6-draw residential example assigns 20%, 20%, 10%, 25%, 15%, and 10% across foundation through final completion.
  • A draw schedule ties payment requests to project milestones, not loose calendar guesses.
  • Construction loan draws move through budget setup, draw request, inspection or verification, lender approval, and fund release.
  • Residential draw schedules need clear milestones for site work, foundation, framing, rough-ins, finishes, and closeout.
  • A Schedule of Values supports the draw schedule by breaking the total contract into billable work categories.
  • Good draw planning reduces payment delays when field progress, photos, materials, change orders, and approvals stay current.

Payment problems start before the draw request, when scope, schedule, budget, and documents drift apart. A draw schedule gives every stakeholder the same payment map before the work reaches the next milestone.

What is a construction draw schedule?

A construction draw schedule is a payment plan that divides a construction contract or loan into milestone-based draws. Each draw lists the work stage, payment trigger, required documentation, approval step, and recipient before funds move. The schedule helps the builder, borrower, owner, lender, and inspector agree on what counts as billable progress.

The project schedule shows when work happens. The draw schedule shows when completed work becomes billable.

For a residential project, the schedule lists stages for site preparation, foundation, framing, rough-ins, drywall, finishes, and final completion. A commercial version uses broader cost codes or phases tied to the Schedule of Values.

The important part is alignment. The draw schedule needs to match the contract, budget, lender requirements, and field reality. If the schedule says a draw happens at framing completion, the team needs a clear definition of framing completion before the project starts.

That definition protects both sides. Contractors know what they need to document before requesting payment. Owners and lenders know what they need to verify before releasing funds.

How does a construction loan draw schedule work?

With a construction loan draw schedule, lenders release loan funds in stages as work reaches approved milestones. The borrower or contractor submits a draw request, the lender checks documents, an inspector or appraiser verifies progress, and the lender releases funds after approval. Each cycle ties field progress to loan controls and payment timing.

Fannie Mae construction-to-permanent guidance states that, in a single-closing transaction, the lender manages disbursement of loan proceeds to the builder, contractor, or authorized suppliers. That is why the draw schedule needs lender-ready detail, not only a contractor payment preference.

The process follows a repeatable path.

The budget is broken into milestones

The project budget comes first. The builder, borrower, and lender need to understand the total contract amount, major cost categories, and milestone structure before the first draw request.

This is where the Schedule of Values matters. It splits the contract into work categories, such as site work, framing, electrical, plumbing, HVAC, finishes, and closeout. From there, the draw schedule turns those categories into a payment sequence.

The contractor or borrower submits a draw request

The request asks for payment tied to completed work. It needs to match the milestone language in the draw schedule.

A clean request includes the draw number, milestone, requested amount, completed work summary, invoices, lien waivers if required, photos, change-order references, and remaining balance.

Loose requests create delays. When rough-in completion is the trigger, the request needs to show which rough-ins are complete and which inspections or approvals support that claim.

The lender or inspector verifies the work

Construction loan draws rely on independent progress verification before funds move. Fannie Mae completion guidance describes completion reports based on an on-site visual inspection and requires visually verifiable exhibits.

That means field evidence matters. Photos, inspection notes, updated schedules, material status, and completed task records all support a faster review.

Lenders release funds after approval

After approval, the lender releases funds according to the loan and draw agreement. CFPB Appendix D also discusses inspection and handling fees, including draw fees, for staged disbursement of construction loan proceeds.

Those details affect cash flow. Missing inspection timing, fee handling, documentation, or lien paperwork stalls the payment request even when the work is on track.

Why Should You Have A Draw Schedule?

It is often challenging to manage cash flow in construction but a draw schedule is a common tool used in construction projects. Even if you are borrowing money, it’s important and it’s actually a requirement if your construction project is being financed through a lender.

Reduce Cash Flow Problems

A draw schedule helps you budget better, so you don’t have to worry as much about having the funding to cover materials and supplies. As each phase of the project is completed, a fresh round of funding is issued to cover the next one.

Protect Your Company

While sometimes contractors can get stiffed at the end of a job like this by owners withholding the last payment, most often having a draw schedule protects you and, thus, your company and employees. You will have a clear picture of what your cash flow will look like throughout the process.

Protects the Owner

Whether you’re doing a private or commercial project, the owner will have more confidence because they will be able to clearly see what’s being done rather than paying in advance for work that has not been completed yet. 

Developing A Construction Draw Schedule

It takes some time and attention to detail to develop a good construction draw schedule and sometimes the lender will develop it for you. However, that does not mean you have to accept their terms, as draw schedules can be negotiated.

Create The Project Schedule

If you’ve been in construction for awhile, you likely have a good idea of the stages of property development and the milestones that make up a construction project. Review previous projects you’ve done to get an accurate idea of how long each phase took and take time to create a reasonable schedule for the project that you’re confident with.

Schedule Your Values 

A Schedule of Values (SOV) includes each work item for your project, its value, and the percentage of completion. For large projects, there may be more items to list, but a simple and basic SOV should include at minimum:

  • Project name/number
  • Name of the contractor
  • Application number/date
  • Work item numbers and descriptions
  • Value of each item
  • Percentage of work completed
  • Value of work completed (past and current periods)
  • Balance remaining for each 
  • Retainage percentage and amount for each item
  • Consent and acknowledgment

The value of each item needs to be as accurate and reasonable as possible so review past job costs to ensure you’re not going to short yourself or your client with incorrect values.



Sample Schedule of Values for a 2000 sq. ft. Custom Home

Cost

% of total

Plans and specs

$2,000

1

Permits, fees, inspections

4,000

2

Impact fee

3,000

1.5

Clear lot, rough grade

1,500

1

Survey

1,000

0.5

Water hookup and fees

3000

1.5

Sewer hookup and fees

3000

1.5

Well, pump, hookup, and water treatment

NA

Septic system and hookup

NA

Excavation and backfill

4,000

2

Foundation and flatwork

12,000

6

Rough Framing

31,000

15

Windows

6,000

3

Exterior doors and hardware

2,000

1

Roofing

5,000

2.5

Siding and ext. trim

10,000

5

Gutters and downspouts

1,000

0.5

Plumbing rough-in

9,000

4.5

Electrical rough-in

8,000

4

HVAC

8,000

4

Insulation

3,000

1.5

Drywall

10,000

5

Stairs

3,000

1.5

Interior trim

7,000

3.5

Interior doors

2,000

1

Painting interior/exterior

7,000

3.5

Cabinets and countertops

12,000

6

Appliances

NA

Lighting Fixtures

2,000

1

Plumbing Fixtures

4,000

2

Floor coverings: wood, tile, carpet, vinyl

12,000

6

Garage doors and opener

2,000

1

Porch, wood deck, or patio

5,500

3

Driveway and walkways

6,000

3

Landscaping

6,000

3

Other

5,000

2.5

TOTAL CONSTRUCTION COST

$200,000

  • Note: Add $30,000 to $40,000 (15% to 20%) for contractor’s overhead and profit, plus an additional $6,000 (3%) for construction financing, and an additional 5% for sales and marketing, if purchased from a developer.

Font: Building Advisor



Simplify Your Draw Schedule

In many cases, the owner of the project or the lender will send inspectors out to review the project so you won’t need a lot of minute details on your draw schedule.

Keep tedious things off of it and include only the milestones you’ll be requesting payments for. For example, the Exterior Finish stage may include:

  • Sidewalks
  • Landscaping
  • Wood trim
  • Caulking
  • Driveways

However, there’s no need to include all of these items on your draw schedule. Simply have “Exterior Finish” as one item.

Calculate The Number Of Draw Requests

Once you have your project divided into clear milestones, take time to think about when and how often you’re going to need funding. This will be dependent on many factors. When do your workers need to get paid? How much of your own money are you spending? Think about retainage. Be as accurate as possible to avoid cash flow disruptions and project delays.

What Is a Typical Construction Draw Schedule?

Draw schedules will vary depending on the project but an example of a typical construction draw schedule looks like this:

  • 20% payment received after the completion of site prep and utility services are completed.
  • 20% is paid after initial framing and utility connections are completed.
  • 20% is dispersed once you complete the interior work.
  • 20% is paid when you finish exterior work.
  • Finally, 20% is received when the project is completed, including cleanup.

While this is a simplified example, it’s just to illustrate how a draw schedule generally works.

Issues to avoid

If you’re not familiar with draw schedules in construction, there are certain things to watch for because the verbiage in a construction draw schedule can be such that it favors one party over the other.

Avoid Vague Language

Vague wording can lead to misunderstandings so make sure the words you use are clear and concise.

Avoid Front End Load Draws

Front-End load draws may seem attractive but ultimately don’t serve the project well. A front-end load draw is when a significant amount of the money for the project (as much as 70%) is distributed before the project is done. This is not fair to the owner and it puts you at risk of going over budget.

Stick To The Schedule

To protect yourself and the buyer, stick to the schedule as outlined by the draw schedule. This will protect your reputation as a builder, and show good faith to the owner.

Save Time and Money with ClockShark

Sign Up Now

No credit card required.

Length Of Construction Draw Schedules

The length of a construction draw schedule will depend on the size and scope of the project, but most draw schedules are set up for one year. Many projects don’t take that long, though, which is why draw schedules are based on percentages of completion rather than dates.

Construction projects are notoriously known for delays due to issues beyond the contractor’s control, such as weather conditions or disruptions in their supply chain. That’s another reason why draw schedules in construction are popular in commercial construction projects.

Since draw schedules are built around milestones, it will depend on how long it will take you to complete the work as well as how long it takes you to get started on it. 

For example, let’s say you’re hired to do a project during the rainy season which prevents the work from getting off the ground for three months. You might only be able to draw a small percentage of the funds to begin with.

Alternatively, if you have a project that will take two months to finish and it’s done in the right amount of time, you can request half the funds the first month and the last half, the second month.

Getting Your Construction Draw Schedules Right

When working in construction, it’s important to have as much data as you can have, to make sure you develop a construction draw schedule that covers your expenses in a way that’s sustainable. Take time to review previous job costs and determine a realistic view of how long the project will take and cost, so you don’t spend money out of your own pocket to cover costs.